36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work?

Review the verified answer and explanation for this Demo Paper India past-paper question on CampusFin.

36 men can complete a piece of work in 18 days. In how many days will 27 men complete the same work? Answer: 24