Find how many man-days to complete the road: 70*35 = 2450 man-days Let d = days required for 40 men to do it. 40d = 2450 d= 40/2450 =61.25
If 70 men can work in 35 days, 40 men complete this work in days?
Review the verified answer and explanation for this ASF Airports Security Force past-paper question on CampusFin.