Let's denote A's rate of work as A, and B's rate of work as B. Given A + B together complete the work in 12 days: (A + B)'s 1 day's work = 1/12 B alone completes the work in 20 days: B's 1 day's work = 1/20 A's 1 day's work = (A + B)'s 1 day's work - B's 1 day's work = 1/12 - 1/20 = (5 - 3) / 60 = 2 / 60 = 1 / 30 A alone will complete the work in 30 days.
If A and B together complete a work in 12 days and B alone can do it in 20 days, how many days will A alone take to complete the work?
Review the verified answer and explanation for this ASF Airports Security Force past-paper question on CampusFin.
Question context
This question is part of 📏 Arithmetic Aptitude within the broader 🧠 Aptitude Mastery subject and appears in the ASF Airports Security Force preparation collection. Reviewing the answer together with nearby questions helps reinforce the underlying concept and identify how it may appear in competitive exams.