For transferring the tunnel alignment through shafts, we adopt the following steps : 1. Hanging two or more plumb lines in the shaft 2. Determining the bearing of the plumb lines i.e. plumb plane 3. Suspending a 35 kg weight by each plumb line 4. Immersing the weights of both the plumb lines in the buckets containing water. The correct sequence of steps is :

Review the verified answer and explanation for this DemoPaper-Pakistan past-paper question on CampusFin.

For transferring the tunnel alignment through shafts, we adopt the following steps : 1. Hanging two or more plumb lines in the shaft 2. Determining the bearing of the plumb lines i.e. plumb plane 3. Suspending a 35 kg weight by each plumb line 4. Immersing the weights of both the plumb lines in the buckets containing water. The correct sequence of steps is : Answer: 1 2 3 4

Question context

This question is part of 🚧 Civil Engineering within the broader 🛠️ Engineering Essentials subject and appears in the DemoPaper-Pakistan preparation collection. Reviewing the answer together with nearby questions helps reinforce the underlying concept and identify how it may appear in competitive exams.