If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good

Review the verified answer and explanation for this DemoPaper-Pakistan past-paper question on CampusFin.

If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good Answer: all the above.

Question context

This question is part of 🚧 Civil Engineering within the broader 🛠️ Engineering Essentials subject and appears in the DemoPaper-Pakistan preparation collection. Reviewing the answer together with nearby questions helps reinforce the underlying concept and identify how it may appear in competitive exams.