Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:

Review the verified answer and explanation for this DemoPaper-Pakistan past-paper question on CampusFin.

Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is: Answer: 16

Question context

This question is part of 📏 Arithmetic Aptitude within the broader 🧠 Aptitude Mastery subject and appears in the DemoPaper-Pakistan preparation collection. Reviewing the answer together with nearby questions helps reinforce the underlying concept and identify how it may appear in competitive exams.