35 workers are employed to complete a construction project in 16 days. Before the project starts, the boss of the company is told that he needs to complete the project in 14 days. Assuming that all the workers work at the same rate, how many more workers does he need to employ in order to complete the project on time?

Review the verified answer and explanation for this PPSC Punjab Public Service Commission past-paper question on CampusFin.

35 workers are employed to complete a construction project in 16 days. Before the project starts, the boss of the company is told that he needs to complete the project in 14 days. Assuming that all the workers work at the same rate, how many more workers does he need to employ in order to complete the project on time? Answer: 5

Question context

This question is part of 📏 Arithmetic Aptitude within the broader 🧠 Aptitude Mastery subject and appears in the PPSC Punjab Public Service Commission preparation collection. Reviewing the answer together with nearby questions helps reinforce the underlying concept and identify how it may appear in competitive exams.