n this case, the total work units are calculated as \(4\text{\ people}\times 40\text{\ minutes}=160\text{\ person-minutes}\) . The time taken for \(8\) people to complete the same work is found by dividing the total work units by the new number of people. This calculation is performed as \(\frac{160\text{\ person-minutes}}{8\text{\ people}}=20\text{\ minutes}\)
if 4 people can do a work in 40 minutes then 8 people can do the same work in ________ minutes: